PMI PMI Certification PMI-001 Questions & Answers

  • Question 591:

    The links between the processes in the Process Groups are often:

    A. Intuitive

    B. Iterative

    C. Measured

    D. Monitored

  • Question 592:

    Work performance information and cost forecasts are outputs of which Project Cost Management process?

    A. Estimate Costs

    B. Plan Cost Management

    C. Determine Budget

    D. Control Costs

  • Question 593:

    Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

    A. Coaching

    B. Avoidance

    C. Consensus

    D. Influencing

  • Question 594:

    The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

    A. start-to-start (SS)

    B. start-to-finish (SF)

    C. finish-to-start (FS)

    D. finish-to-finish (FF)

  • Question 595:

    Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

    A. Histograms

    B. Scatter diagrams

    C. Flowcharts

    D. Checksheets

  • Question 596:

    Projects are undertaken by an organization to support the:

    A. Product performance.

    B. Budget process.

    C. Collective capabilities.

    D. Organizational strategy.

  • Question 597:

    What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

    A. 0.45

    B. 0.56

    C. 0.70

    D. 1.36

  • Question 598:

    A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

    A. Historical information and the lessons-learned database.

    B. Historical information and the stakeholder register.

    C. Organizational process assets and the lessons-learned database.

    D. Project documents and historical information.

  • Question 599:

    Which of the following is a narrative description of products, services, or results to be delivered by a project?

    A. Project statement of work

    B. Business case

    C. Accepted deliverable

    D. Work performance information

  • Question 600:

    The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

    A. Supportive

    B. Leading

    C. Neutral

    D. Resistant

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.