PMI PMI Certifications PMI-001 Questions & Answers

  • Question 491:

    An output of the Create WBS process is:

    A. Scope baseline.

    B. Project scope statement.

    C. Organizational process assets.

    D. Requirements traceability matrix.

  • Question 492:

    Change requests are an output from which Project Integration Management process?

    A. Direct and Manage Project Execution

    B. Develop Project Management Plan

    C. Close Project

    D. Develop Project Charter

  • Question 493:

    When can pre-assignment of project team members occur?

    A. When the project uses capital expenditures

    B. When the required staff can be acquired from outside sources

    C. When the project would be ignored due to travel expenses

    D. When the project is the result of specific people being promised as part of a competitive proposal

  • Question 494:

    What type of project structure is a hierarchically organized depiction of the resources by type?

    A. Organizational breakdown structure (OBS)

    B. Resource breakdown structure (RBS)

    C. Work breakdown structure (WBS)

    D. Project breakdown structure (PBS)

  • Question 495:

    Cost baseline is an output of which of the following processes?

    A. Control Costs

    B. Determine Budget

    C. Estimate Costs

    D. Estimate Activity Resources

  • Question 496:

    Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

    A. The Delphi technique

    B. Nominal group technique

    C. Affinity diagram

    D. Brainstorming

  • Question 497:

    At which point of the project is the uncertainty the highest and the risk of failing the greatest?

    A. Final phase of the project

    B. Start of the project

    C. End of the project

    D. Midpoint of the project

  • Question 498:

    To which process is work performance information an input?

    A. Administer Procurements

    B. Direct and Manage Project Execution

    C. Create WBS

    D. Perform Qualitative Risk Analysis

  • Question 499:

    Which defines the portion of work included in a contract for items being purchased or acquired?

    A. Procurement management plan

    B. Evaluation criteria

    C. Work breakdown structure

    D. Procurement statement of work

  • Question 500:

    What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

    A. Decomposition

    B. Benchmarking

    C. Inspection

    D. Checklist analysis

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.