Exam Details

  • Exam Code
    :PMI-001
  • Exam Name
    :Project Management Professional
  • Certification
    :PMI Certifications
  • Vendor
    :PMI
  • Total Questions
    :920 Q&As
  • Last Updated
    :Jun 01, 2025

PMI PMI Certifications PMI-001 Questions & Answers

  • Question 481:

    Conflict should be best addressed in which manner?

    A. Early, in private, using a direct, collaborative approach

    B. Early, in public, using an indirect, collaborative approach

    C. Early, in private, using an indirect, cooperative approach

    D. As late as possible, in public, using a direct, confrontational approach

  • Question 482:

    Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

    A. Budget plan

    B. Resource plan

    C. Scope plan

    D. Strategic plan

  • Question 483:

    What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

    A. Organizational process assets

    B. Enterprise environmental factors

    C. Project management processes

    D. Project scope management plan

  • Question 484:

    The Human Resource Management processes are:

    A. Develop Human Resource Plan, Acquire Project Team, Develop Project Team, and Manage Project Team.

    B. Acquire Project Team, Manage Project Team, Manage Stakeholder Expectations, and Develop Project Team.

    C. Acquire Project Team, Develop Human Resource Plan, Conflict Management, and Manage Project Team.

    D. Develop Project Team, Manage Project Team, Estimate Activity Resources, and Acquire Project Team.

  • Question 485:

    Which is one of the major outputs of Sequence Activities?

    A. Responsibility assignment matrix (RAM)

    B. Work breakdown structure (WBS) update

    C. Project schedule network diagram

    D. Mandatory dependencies list

  • Question 486:

    Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

    A. Control chart

    B. Earned value

    C. Variance

    D. Trend

  • Question 487:

    The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

    A. US$158,700

    B. US$172,500

    C. US$187,500

    D. US$245,600

  • Question 488:

    If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst- case duration is 14 weeks, how many weeks is the expected duration of the activity?

    A. One

    B. Five

    C. Six

    D. Seven

  • Question 489:

    Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

    A. Estimate Costs

    B. Estimate Activity Resources

    C. Control Costs

    D. Determine Budget

  • Question 490:

    Plan Risk Management is the process of defining how to:

    A. Communicate identified risks to the project stakeholders.

    B. Conduct risk management activities for a project.

    C. Analyze the impact a specific risk may have on the project.

    D. Address unexpected risks that may occur during a project.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.