Exam Details

  • Exam Code
    :PMI-001
  • Exam Name
    :Project Management Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :920 Q&As
  • Last Updated
    :Jun 01, 2025

PMI PMI Certification PMI-001 Questions & Answers

  • Question 281:

    Which is an output of the Collect Requirements process?

    A. Requirements traceability matrix

    B. Project scope statement

    C. WBS dictionary

    D. Work performance measurements

  • Question 282:

    Which activity may occur at project or phase closure?

    A. Acceptance of deliverables

    B. Change requests

    C. Project management plan updates

    D. Benchmarking

  • Question 283:

    Which of the following is an input to Direct and Manage Project Execution?

    A. Performance reports

    B. Project charter

    C. Outputs from planning processes

    D. Enterprise environmental factors

  • Question 284:

    During project selection, which factor is most important?

    A. Types of constraints

    B. Internal business needs

    C. Budget

    D. Schedule

  • Question 285:

    The staffing management plan is part of the:

    A. organizational process assets.

    B. resource calendar.

    C. human resource plan.

    D. Develop Project Team process.

  • Question 286:

    In the basic communication model, which term refers to the method that is used to convey the message?

    A. Decode

    B. Encode

    C. Medium

    D. Noise

  • Question 287:

    Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

    A. Cost Plus Award Fee Contract (CPAF)

    B. Firm-Fixed -Price Contract (FFP)

    C. Time and Material Contract (TandM)

    D. Cost Plus Incentive Fee Contract (CPIF)

  • Question 288:

    Which characteristics do effective project managers possess?

    A. Project management knowledge, performance skills, and personal effectiveness

    B. Preparedness, project management knowledge, and personality characteristics

    C. General management, preparedness, and project management knowledge

    D. Assertiveness, collaboration, and performance skills

  • Question 289:

    Risk exists the moment that a project is:

    A. planned.

    B. conceived.

    C. chartered.

    D. executed.

  • Question 290:

    Who determines which dependencies are mandatory during the Sequence Activities process?

    A. Project manager

    B. External stakeholders

    C. Internal stakeholders

    D. Project team

Related Exams:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.