Which does a Project Manager produce to define and control the work to be done?
A. Configuration Item Record
B. Stage scope tolerance
C. Team Plan
D. Work Package
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
Which describes risk probability?
A. Level of risks which the project can tolerate before escalating to the Project Board
B. Probable effect on the project delivering its objectives
C. Timeframe within which the risk may occur
D. A measure of the likelihood of the risk occurring
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
A. Off-specifications
B. Follow-on action recommendations
C. Issue Register
D. Risk Register
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
A. The preference of the Project Manager
B. Having insufficient authority to perform the role
C. Having insufficient time to perform the role
D. The need to involve key stakeholders on the project management team
Which is NOT a requirement of a Stage Plan?
A. Produced to an appropriate level of detail to enable day-to-day control
B. Produced near to the end of the previous management stage
C. Approved and signed-off by Project Assurance
D. Approved at the end of a management stage
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A. Senior User
B. Executive
C. Corporate/programme management
D. Senior Supplier
Which is a purpose of quality planning?
A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information
Which of the following statements about customer's quality expectations and acceptance criteria are true?
1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
2.Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.