  • Question 141:

    Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.

    A. the measurement of benefits NOT yet realized

    B. the handover of products

    C. open issues and risks

    D. the release of resources

  • Question 142:

    In what process is the authorization to deliver the project's products given?

    A. Starting up a Project

    B. Initiating a Project

    C. Managing a Stage Boundary

    D. Directing a Project

  • Question 143:

    Which of the following is NOT part of quality planning?

    A. Define quality responsibilities

    B. Gain acceptance of the project product

    C. Agree acceptance criteria

    D. Set quality tolerances

  • Question 144:

    Which should be provided by a project mandate?

    A. Terms of reference

    B. Detailed Business Case

    C. Stage tolerances

    D. Initiation Stage Plan

  • Question 145:

    Which is an objective of the Starting up a Project process?

    A. Identify who will be responsible for creating the Project Plan

    B. Agree how the project will be monitored and controlled after initiation

    C. Authorize the Project Manager to proceed with the initiation stage

    D. Agree how issues and changes will be identified, assessed and controlled

  • Question 146:

    Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project.

    A. Management strategies

    B. Plan

    C. Stakeholder interests

    D. Time-driven controls

  • Question 147:

    When considering risks, which describes an opportunity in a project?

    A. An uncertain event that could have a negative impact on objectives

    B. An uncertain event that could have a favourable impact on objectives

    C. An event that has occurred resulting in a negative impact on objectives

    D. An event that has occurred resulting in a favourable impact on objectives

  • Question 148:

    Which of the following statements about lines of authority and reporting are true? 1, The Project Manager has day-to-day control for a management stage within the limits laid,

    2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.

    A. Only 1 is true

    B. Only 2 is true

    C. Both 1 and 2 are true

    D. Neither 1 or 2 are true

  • Question 149:

    Which may be funded from a risk budget?

    A. Corrections due to off-specifications

    B. Impact analysis of requests for change

    C. Implementation of a fallback plan

    D. Preparation of the Risk Management Strategy

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only EXIN exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your EX0-002 exam preparations and EXIN certification application, do not hesitate to visit our Vcedump.com to find your solutions here.