  • Question 1161:

    The procurement process that documents agreements and related documentation for future reference is known as:

    A. Plan Procurements.

    B. Control Procurements.

    C. Close Procurements.

    D. Conduct Procurements.

  • Question 1162:

    The links between the processes in the Process Groups are often:

    A. Intuitive

    B. Iterative

    C. Measured

    D. Monitored

  • Question 1163:

    The scope of a project cannot be defined without some basic understanding of how to create the specified:

    A. objectives

    B. schedule

    C. product

    D. approach

  • Question 1164:

    The creation of an internet site to engage stakeholders on a project is an example of which type of communication?

    A. Push

    B. Pull

    C. Interactive

    D. Iterative

  • Question 1165:

    Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

    A. Resource breakdown structure

    B. Staffing management plan

    C. Project organizational chart

    D. Scope management plan

  • Question 1166:

    The process of formalizing acceptance of the completed project deliverables is known as:

    A. Validate Scope.

    B. Close Project or Phase.

    C. Control Quality.

    D. Verify Scope.

  • Question 1167:

    An output of Control Schedule is:

    A. A project schedule network diagram

    B. A schedule management plan

    C. Schedule data

    D. Schedule forecasts

  • Question 1168:

    What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

    A. Failure modes and effects analysis

    B. Design of experiments

    C. Quality checklist

    D. Risk analysis

  • Question 1169:

    When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

    A. Bottom-up

    B. Parametric

    C. Analogous

    D. Three-point

  • Question 1170:

    Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

    A. Cost management plan

    B. Quality management plan

    C. Communications management plan

    D. Risk management plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.