  • Question 1151:

    Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

    A. Risk and uncertainty increase; the cost of changes increases.

    B. Risk and uncertainty increase; the cost of changes decreases.

    C. Risk and uncertainty decrease; the cost of changes increases.

    D. Risk and uncertainty decrease; the cost of changes decreases.

  • Question 1152:

    Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

    A. Build vs. buy

    B. Expert judgment

    C. Alternatives identification

    D. Product analysis

  • Question 1153:

    Most experienced project managers know that:

    A. every project requires the use of all processes in the PMBOK?Guide.

    B. there is no single way to manage a project.

    C. project management techniques are risk free.

    D. there is only one way to manage projects successfully.

  • Question 1154:

    What is an objective of the Develop Project Team process?

    A. Feelings of trust and improved cohesiveness

    B. Ground rules for interaction

    C. Enhanced resource availability

    D. Functional managers becoming more involved

  • Question 1155:

    The product scope description is used to:

    A. Gain stakeholders' support for the project.

    B. Progressively elaborate the characteristics of the product, service, or result.

    C. Describe the project in great detail.

    D. Define the process and criteria for accepting a completed product, service, or result.

  • Question 1156:

    Which technique is used in Perform Quantitative Risk Analysis?

    A. Sensitivity analysis

    B. Probability and impact matrix

    C. Risk data quality assessment

    D. Risk categorization

  • Question 1157:

    Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

    A. Histograms

    B. Scatter diagrams

    C. Flowcharts

    D. Checksheets

  • Question 1158:

    The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

    A. start-to-start (SS)

    B. start-to-finish (SF)

    C. finish-to-start (FS)

    D. finish-to-finish (FF)

  • Question 1159:

    Work performance information and cost forecasts are outputs of which Project Cost Management process?

    A. Estimate Costs

    B. Plan Cost Management

    C. Determine Budget

    D. Control Costs

  • Question 1160:

    Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

    A. Coaching

    B. Avoidance

    C. Consensus

    D. Influencing

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.