  • Question 1171:

    Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

    A. Organizational process assets

    B. A work breakdown structure

    C. The project management plan

    D. Enterprise environmental factors

  • Question 1172:

    The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

    A. Supportive

    B. Leading

    C. Neutral

    D. Resistant

  • Question 1173:

    Which of the following is a narrative description of products, services, or results to be delivered by a project?

    A. Project statement of work

    B. Business case

    C. Accepted deliverable

    D. Work performance information

  • Question 1174:

    A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

    A. Historical information and the lessons-learned database.

    B. Historical information and the stakeholder register.

    C. Organizational process assets and the lessons-learned database.

    D. Project documents and historical information.

  • Question 1175:

    Projects are undertaken by an organization to support the:

    A. Product performance.

    B. Budget process.

    C. Collective capabilities.

    D. Organizational strategy.

  • Question 1176:

    What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

    A. 0.45

    B. 0.56

    C. 0.70

    D. 1.36

  • Question 1177:

    DRAG DROP

    Match each tool or technique to its corresponding Project Risk Management process. Click on the tool or technique on the left and drag it to the appropriate gray box in the middle.

    Select and Place:

  • Question 1178:

    DRAG DROP

    Match the role with its corresponding job description.

    Select and Place:

  • Question 1179:

    DRAG DROP

    A project manager is reviewing the different tools and techniques used to perform a quantitative risk analysis. Match the tool and techniques with the appropriate result.

    Select and Place:

  • Question 1180:

    DRAG DROP

    Match the process with its corresponding process group.

    Select and Place:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.