  • Question 1131:

    A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

    A. Efficient

    B. Effective

    C. Push

    D. Pull

  • Question 1132:

    A large portion of a projects budget is typically expended on the processes in which Process Group?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Closing

  • Question 1133:

    Which input provides suppliers with a clear set of goals, requirements, and outcomes?

    A. Procurement statement of work

    B. Purchase order

    C. Source selection criteria

    D. Bidder conference

  • Question 1134:

    An input to the Manage Project Team process is:

    A. Work performance reports.

    B. Change requests.

    C. Activity resource requirements.

    D. Enterprise environmental factors.

  • Question 1135:

    During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

    A. Monitor and Control Project Work

    B. Perform Quality Assurance

    C. Close Project or Phase

    D. Control Scope

  • Question 1136:

    Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

    A. Mandatory

    B. Discretionary

    C. Internal

    D. External

  • Question 1137:

    The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

    A. Develop Project Team.

    B. Manage Project Team.

    C. Acquire Project Team.

    D. Plan Human Resource Management.

  • Question 1138:

    A technique used to determine the cause and degree of difference between baseline and actual performance is:

    A. Product analysis.

    B. Variance analysis.

    C. Document analysis.

    D. Decomposition.

  • Question 1139:

    An input to the Plan Cost Management process is:

    A. Cost estimates

    B. Resource calendars

    C. The project charter

    D. The risk register

  • Question 1140:

    An input to the Plan Stakeholder Management process is:

    A. The project charter.

    B. The stakeholder analysis.

    C. A communication management plan.

    D. A stakeholder register.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.