  • Question 1121:

    Which item is a formal proposal to modify any document, deliverable, or baseline?

    A. Change request

    B. Requirements documentation

    C. Scope baseline

    D. Risk urgency assessment

  • Question 1122:

    The Identify Stakeholders process is found in which Process Group?

    A. Initiating

    B. Monitoring and Controlling

    C. Planning

    D. Executing

  • Question 1123:

    An input to Develop Project Charter is a/an:

    A. Business case.

    B. Activity list.

    C. Project management plan.

    D. Cost forecast.

  • Question 1124:

    The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

    A. Collect Requirements.

    B. Conduct Procurements.

    C. Estimate Activity Durations.

    D. Estimate Activity Resources.

  • Question 1125:

    Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

    A. Procurement documents

    B. Communications plan

    C. Project charter

    D. Stakeholder register

  • Question 1126:

    Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?

    A. Control charts

    B. Pareto diagrams

    C. Ishikawa diagrams

    D. Checksheets

  • Question 1127:

    Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

    A. Facilitation techniques

    B. Expert judgment

    C. Analytical techniques

    D. Variance analysis

  • Question 1128:

    Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?

    A. Power/influence grid

    B. Power/interest grid

    C. Influence/impact grid

    D. Salience model

  • Question 1129:

    A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

    A. Benchmarking.

    B. Context diagrams.

    C. Brainstorming.

    D. Prototyping.

  • Question 1130:

    Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?

    A. Feedback analysis

    B. Stakeholder analysis

    C. Communication management plan

    D. Stakeholder management plan

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.