  • Question 521:

    Which item is a cost of conformance?

    A. Training

    B. Liabilities

    C. Lost business

    D. Scrap

  • Question 522:

    Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

    A. Continuous

    B. Discrete

    C. Regulated

    D. Arbitrary

  • Question 523:

    A graphic display of project team members and their reporting relationships is known as a:

    A. Resource calendar.

    B. Project organization chart.

    C. Resource breakdown structure (RBS).

    D. Responsibility assignment matrix (RAM).

  • Question 524:

    The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

    A. recognition and rewards

    B. compliance

    C. staff acquisition

    D. training needs

  • Question 525:

    The following is a network diagram for a project. The shortest non-critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 16

  • Question 526:

    The following is a network diagram for a project.

    The critical path for the project is how many days in duration?

    A. 10

    B. 12

    C. 14

    D. 17

  • Question 527:

    Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

    A. Influencing

    B. Motivation

    C. Negotiation

    D. Trust building

  • Question 528:

    An example of a group decision-making technique is:

    A. nominal group technique

    B. majority

    C. affinity diagram

    D. multi-criteria decision analysis

  • Question 529:

    Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

    A. Procurement documents

    B. Inspection and audits

    C. Estimate budget

    D. Risk register

  • Question 530:

    Which type of graphic is displayed below?

    A. Work breakdown structure

    B. Context diagram

    C. Control chart

    D. Pareto diagram

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.