  • Question 421:

    The component of the risk management plan that documents how risk activities will be recorded is called:

    A. tracking

    B. scoping

    C. timing

    D. defining

  • Question 422:

    Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

    A. Information management systems

    B. Work performance reports

    C. Stakeholder analysis

    D. Data gathering and representation

  • Question 423:

    A project manager requesting industry groups and consultants to recommend project intervention is relying on:

    A. Communication models.

    B. Stakeholder participation.

    C. Expert judgment

    D. Enterprise environmental factors.

  • Question 424:

    The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

    A. appetite

    B. tolerance

    C. threshold

    D. management

  • Question 425:

    The following is a network diagram for a project.

    What is the critical path for the project?

    A. A-B-D-G

    B. A-B-E-G

    C. A-C-F-G

    D. A-C-E-G

  • Question 426:

    The following is a network diagram for a project.

    The total float for the project is how many days?

    A. 3

    B. 5

    C. 7

    D. 9

  • Question 427:

    Tools and techniques used in Direct and Manage Project Work include:

    A. Process analysis and expert judgment

    B. Analytical techniques and a project management information system

    C. Performance reviews and meetings

    D. Expert judgment and meetings

  • Question 428:

    Which Process Group includes the Manage Stakeholder Engagement process?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Initiating

  • Question 429:

    Funding limit reconciliation is a tool and technique of which Project Cost Management process?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management

    D. Determine Budget

  • Question 430:

    In complex projects/ initiating processes should be completed:

    A. Within a work package.

    B. In each phase of the project.

    C. To estimate schedule constraints.

    D. To estimate resource allocations.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.