  • Question 221:

    Which of the following is an example of the simplest fixed-price contract?

    A. Purchase requisition

    B. Purchase order

    C. Verbal agreement

    D. Request for quote

  • Question 222:

    Which technique helps to determine the risks that have the most potential impact on a project?

    A. Cost risk simulation analysis

    B. Expected monetary value analysis

    C. Modeling and simulation

    D. Sensitivity analysis

  • Question 223:

    Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

    A. Plan Risk Responses

    B. Manage Stakeholder Expectations

    C. Define Scope

    D. Report Performance

  • Question 224:

    Which process involves identifying and documenting the logical relationships between project activities?

    A. Develop Schedule

    B. Sequence Activities

    C. Create WBS

    D. Applying leads and lags

  • Question 225:

    Which activity involves ensuring that the composition of a projects configuration items is correct?

    A. Configuration Identification

    B. Configuration Status Accounting

    C. Configuration Verification and Audit

    D. Configuration Quality Assurance

  • Question 226:

    Which of the following documents allows the project manager to assess risks that may require near term action?

    A. Probability and impact matrix

    B. Contingency analysis report

    C. Risk urgency assessment

    D. Rolling wave plan

  • Question 227:

    In which process is a project manager identified and given the authority to apply resources to project activities?

    A. Acquire Project Team

    B. Develop Project Management Plan

    C. Manage Project Execution

    D. Develop Project Charter

  • Question 228:

    Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

    A. Monitor and Control Risks

    B. Plan Risk Management

    C. Perform Qualitative Risk Analysis

    D. Perform Quantitative Risk Analysis

  • Question 229:

    Which is a communication method used in the Report Performance process?

    A. Expert judgment

    B. Project management methodology

    C. Stakeholder analysis

    D. Status review meetings

  • Question 230:

    Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

    A. Project Time Management

    B. Project Cost Management

    C. Project Scope Management

    D. Project Human Resource Management

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.