  • Question 241:

    In which process might a project manager use risk reassessment as a tool and technique?

    A. Perform Qualitative Risk Analysis

    B. Monitor and Control Risk

    C. Monitor and Control Project Work

    D. Plan Risk Responses

  • Question 242:

    In which domain of project management would a Pareto chart provide useful information?

    A. Project Scope Management

    B. Project Time Management

    C. Project Communications Management

    D. Project Quality Management

  • Question 243:

    Which of the following is an input to the Direct and Manage Project Execution process?

    A. Approved change requests

    B. Approved contract documentation

    C. Work performance information

    D. Rejected change requests

  • Question 244:

    Which of the following factors is lowest at the start of the project?

    A. Cost of changes

    B. Stakeholder influences

    C. Risk

    D. Uncertainty

  • Question 245:

    The project scope statement and resource calendars are inputs to which Project Time Management process?

    A. Sequence Activities

    B. Estimate Activity Resources

    C. Develop Schedule

    D. Control Schedule

  • Question 246:

    Which process determines the risks that might affect the project?

    A. Perform Qualitative Risk Analysis

    B. Identify Risks

    C. Plan Risk Management

    D. Perform Quantitative Risk Analysis

  • Question 247:

    In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

    A. Team meetings

    B. Subcontracting teams

    C. Virtual teams

    D. Teamwork

  • Question 248:

    What causes replanning of the project scope?

    A. Project document updates

    B. Project scope statement changes

    C. Variance analysis

    D. Change requests

  • Question 249:

    Which of the following is an output of the Distribute Information process?

    A. Project calendar

    B. Communications management plan

    C. Organizational process assets updates

    D. Project document updates

  • Question 250:

    What provides information regarding the ways people, teams, and organizational units behave?

    A. Organizational chart

    B. Organizational theory

    C. Organizational structure

    D. Organizational behavior

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.