Microsoft 70-348 Online Questions & Answers

  • Question 31:

    You are a portfolio manager for an organization that uses Microsoft PPM to manage projects. You plan to implement Power BI. You need to import into Power BI by using the Microsoft Project Online content pack. What should you do?

    A. In the Power BI Add content pack library, connect to Microsoft PPM by using the URL for the organization.
    B. In the Power BI Services content pack library, connect to Microsoft PPM using the Microsoft PPM URL for the organization.
    C. In the Power BI Import or Connect to Data tool, select Databases and more. Then, connect to Microsoft PPM by using the database alias for the organization.
    D. In the Power BI My Organization content pack library, connect to Microsoft PPM by using the PWA URL for the organization.

  • Question 32:

    You are an administrator for an organization that uses Microsoft PPM. A project manager is building a team for a project. The project manager reports that a newly hired resource is not visible in Build Team. You need to ensure that newly added users are available in Build Team. What should you do?

    A. Edit the user account set Default Booking Type as Committed
    B. Edit the user account select the check box Team Assignment Pool.
    C. Edit the user account select the checkbox User can be assigned as a resource.
    D. Edit the user account set the account status to Active

  • Question 33:

    Your organization uses Microsoft PPM and Power BI to manage projects. You create status reports for projects by using Microsoft Excel files and Power BI Desktop. You plan to combine several specific reports into a single Power BI

    dashboard.

    For each of the following statements, select Yes if the statement is true. Otherwise, select No.

    Hot Area:

  • Question 34:

    Your organization is in the process of implementing Microsoft PPM.

    You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects..

    On the Task Settings and Display page, what should you do?

    A. Set the tracking method to Free form
    B. Select the check box Force project managers to use the progress reporting method specified above for all projects.
    C. Clear the check box Force project managers to use the progress reporting method specified above for all projects
    D. Set the tracking method to Percent of work complete

  • Question 35:

    This question requires that you evaluate the underlined text to determine if it is correct.

    To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.

    Review the underlined text If it makes the statement correct select "No change is needed." If the statement is incorrect select the answer choice that makes the statement correct

    A. No change is needed.
    B. Capacity Planning page
    C. Resource Plan view in Microsoft Project
    D. Manage Users page

  • Question 36:

    You are a resource manager in an organization that uses Microsoft PPM for resource management You manage two teams, one local and one remote. Project managers are instructed to always submit resource requests based on generic

    roles instead of named resources. Resource managers replace the generic resources with available named resources.

    Project managers must not start work on projects that have generic resources assigned.

    You need to replace proposed requests with committed, named resources.

    Which three actions should you perform? Each correct answer presents part of the solution.

    A. Open resource requests.
    B. Select both the generic and named resource.
    C. Replace the generic resource with a named resource.
    D. Click Build Team.
    E. Select Replace., and accept and confirm the resource.

  • Question 37:

    You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project Resources have been working on the project for six months.

    You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.

    Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order

    Select and Place:

  • Question 38:

    You are a project manager for an organization that uses visibility projects in Microsoft PPM. For each of the following statements, select Yes if the statement is true. Otherwise, select No.

    Hot Area:

  • Question 39:

    You are the administrator for an organization that uses Microsoft PPM. The IT department has 10 developers. You assign all date developers to a team named Developers. The IT manager plans to use the team feature of Microsoft PPM.

    You need to ensure that all project managers can use Team assign instead of Resource assign

    What should you do to finish the Developers team configuration?

    A. Create a generic resource named Developers that is not assigned to the Developers team. Select the Team Assignment Pool option for the resource.
    B. Create a generic resource named Developers
    C. Create a generic resource named Developers Assign the resource to the Developers team.
    D. Create a generic resource named Developers that is assigned to the Developers team. Select the Team Assignment Pool option for the resource.

  • Question 40:

    An organization uses Microsoft PPM to manage content related to projects.

    You need to prevent Microsoft PPM from creating a project site when a new project is created.

    Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

    Select and Place:

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Microsoft exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 70-348 exam preparations and Microsoft certification application, do not hesitate to visit our Vcedump.com to find your solutions here.