  • Question 21:

    Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the Manufacturing Cloud?

    A. Use ibots to create the report.
    B. Use Business Intelligence answers to create the report.
    C. Use the Manufacturing subject area to select the report columns and create the report.
    D. Use Business Intelligence publisher to create a template and use that template to create the report.

  • Question 22:

    The Cost Accountant has reported to the Production Supervisor that the Work Order transactions are not getting transferred to Costing. Identify the reason for work order transactions not getting transferred to Costing.

    A. The Manage Item Rules setup is not complete.
    B. The Costing Interfaced Attribute is enabled in the resource definition.
    C. The item was made inactive after the Work Order transaction.
    D. The Costing Interfaced Attribute is not enabled in the resource definition.

  • Question 23:

    Your customer has defined the work definitions. They have created and saved a new version for the work definition and want to edit that work definition. Which two attributes cannot be updated using the Edit Work Definition Details action?

    A. State Date
    B. Costing Priority
    C. Version
    D. Production Priority

  • Question 24:

    In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.

    A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost

    accounting. Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.

    A. Publish cost planning scenario to Accounting.
    B. Build cost planning scenario and perform cost roll up.
    C. Create Accounting Distributions.
    D. Transfer transactions from production to Costing.
    E. Define a cost planning scenario with Material, Resource, Overhead cost plans, and work definition.
    F. Transfer Transactions from Inventory to Costing.

  • Question 25:

    A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts. Determine the available capacity of the resource R1 for that week.

    A. 78 hours
    B. 76 hours
    C. 60 hours
    D. 70 hours

  • Question 26:

    A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours. The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon. What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?

    A. 8:00 PM
    B. 12:30 PM
    C. 2:00 PM
    D. 4:00 PM
    E. 1:00 PM

  • Question 27:

    Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the process of defining Work Definition and Operations. However, this user is unable to assign an ad hoc item, Grease, to an operation. Identify the reason.

    A. The user doesn't have Override Item Structure Components in the Work Definition privileges.
    B. An item cannot be assigned on an ad hoc basis.
    C. The user doesn't have access to the PIM module.
    D. The user doesn't have Data access to create item structure.

  • Question 28:

    During a Manufacturing Cloud implementation, the Production Supervisor wants to close the work orders for last month and wants to make sure that the work orders include the correct cost. Identify the approach to be taken by the Production Supervisor.

    A. The Production Supervisor need not include cost variances while costing last month's work orders because those can be applied directly in subledger accounting.
    B. The Production Supervisor needs to include all costs and variances in last month's work orders and close them; however, the work orders where updates are expected, should not be closed.
    C. The Production Supervisor should make sure that all costs are included while closing last month's work orders; however, variances can be included after closing the work orders.
    D. Work order costs can be updated anytime regardless of the status of the work order.

  • Question 29:

    In your customer's manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its

    supplies form the Warehouse subinventory through automatically created Movement Requests.

    Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?

    A. Batch Wave Movement Requests
    B. Pick Wave Movement Requests
    C. Replenishment Requests
    D. Requisition Movement Requests

  • Question 30:

    A manufacturing plant works for two shifts of 8 hours each. The Manufacturing user wants a work center resource R1 of 4 units to be available during a nonworking time outside the regular shift on a particular day. Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.

    A. Click Outside the existing Shift time on a Specific Date> Create Work Center page> Click the Resource Availability tab> Click Add icon> Select R1 from Resource Drop-down list> Enter 4 in Default Units Availability column.
    B. Click Inside the existing Shift time on a Specific Date> Action Menu> Select Create Resource exception> Populate Start and Duration Field> Resource Availability region> Populate 4 units in Default Availability column.
    C. Click Inside the existing Shift time on a Specific Date>Create Work Center page>Click the Resource Availability tab>Click Add icon> Select R1 from Resource Drop-down list> Enter4 in Default Units Available.
    D. Click Outside the existing Shift time on a Specific Date> Action Menu> Select Create Resource exception> Populate Start and Duration Field> Resource Availability and Overrides Region> Populate 4 units in Availability Override column.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Oracle exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your 1Z0-1075-20 exam preparations and Oracle certification application, do not hesitate to visit our Vcedump.com to find your solutions here.