Question 44 of 65
0% complete
Q44 Single choice

A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced.
The client is only focused on benefits.

Which of the following actions should the program manager take?