Question 42 of 65
0% complete
Q42 Single choice

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected.
The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized After further analysis of the performance indicators the program manager should do which of the following*?