AACE-PSP Web TestEngine demo

Exit VCEDump AACE-PSP Planning & Scheduling Professional (PSP)
Question 14 of 18
0% complete
Q14 Single choice

There is only enough room for a maximum of 4 cranes to be placed on-site.
Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Question 14 diagram