Q13 Single choice

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration.

What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?