Q57 Drag & drop

DRAG DROP

A recent power Outage caused email services to go down. A sever administrator also received alerts from the datacenter's UPS.

After some investigation, the server administrator learned that each POU was rated at a maximum Of 12A.

INSTRUCTIONS

Ensure power redundancy is implemented throughout each rack and UPS alarms are resolved. Ensure the maximum potential PDU consumption does not exceed 80% or 9.6A).

1. PDU selections must be changed using the pencil icon.
2. VM Hosts 1 and 2 and Mail Relay can be moved between racks.
3. Certain devices contain additional details.

Drag each option into the matching blank slot.