Q21 Single choice

While performing a cost-benefit analysis, the Product Owner of a project determined that the project has 45% probability of incurring a loss of $800,000 due to the latest Land Reform Bill.

Which of the following techniques is being used by the Product Owner to perform cost-benefit analysis?