Q28 Multiple choice

In the Daily Scrum, the Product Owner applauds every Developer who moves a Sprint Backlog item to completion. The Product Owner wants to encourage the Developers to make progress visible on the burn-down chart. Select the two best options for the Scrum Master to take. (Choose two.)

Select all that apply.