Q81 Single choice Mark for later Project managers use velocity to determine: A If the team is committing to an appropriate amount of work for the iteration. B How much work each team member is capable of completing during an iteration. C How much work teams that are similar in size are capable of completing during an iteration. D If the Product Owner is prioritizing work appropriately in preparation for iteration planning. Correct answer