Q5
Single choice
A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following cost estimate:
$150 per hour, estimated time to completion=40 hours The landscaper has completed 35 hours of work.
Which of the following is the Earned Value of this portion of the project?