Question 27 of 35
0% complete
Q27 Single choice

A project to replace an old sales and merchandising system with a new version based on modern platforms, will use an Agile lifecycle with iterations of fixed length.
The project objectives include:

Delivery within 6 months of the start of the first iteration, in 3 releases, to be accomplished by a team that will contain all resources deemed necessary to achieve this Quality of delivered product to meet customer acceptance criteria
A test objective, derived from discussion with the customers, has been set as follows: "Each release shall deliver usability that is better than that of the previous system for the equivalent functionality"

Which S.M.A.R.T. criteria are met by this objective?

1. Specific
2. Measurable
3. Achievable
4. Relevant
5. Timely