ISTQB-CT-TAE Web TestEngine demo

Exit VCEDump ISTQB-CT-TAE ISTQB Certified Tester Test Automation Engineer
Question 17 of 25
0% complete
Q17 Single choice

A regression test suite consist of 500 test cases which are all executed manually. The business case for a pilot project is based on the adoption of test automation using a commercial tool that will reduce the execution time by a factor of 90% for 100% of the tests in the regression test suite. The pilot project lasted one month ( as planned)- and you are currently its results. At the end of the pilot project, 40% of the regression tests have been automated and their execution time has been reduce by 60%.

Which of the following statements is TRUE in this scenario?

Sign in to mark questions