What is one of the Lean budget Guardrails?
A. Objective measurements
B. Continuous Business Owner engagement
C. Participatory budgeting
D. Spending caps for each ART
Which statement is true about Iteration planning for Kanban teams?
A. Kanban teams estimate their velocity
B. Kanban teams publish Iteration goals
C. Kanban teams do not commit to service level agreements
D. Kanban teams find high value in trying to plan the Iteration in detail
What is the formula to calculate flow efficiency?
A. Total wait time / Flow time [Total wait time divided by Flow time]
B. Total active time / Flow time [Total active time divided by Flow time]
C. Total wait time + Flow time [Total wait time plus Flow time]
D. Total active time + Flow time [Total active time plus Flow time]
Who is responsible for managing the Portfolio Kanban?
A. Product Management
B. Release Train Engineer
C. Solution Management
D. Lean Portfolio Management
How can trust be gained between the business and development?
A. Automate the delivery pipeline
B. Deliver predictability
C. Release new value to production every day
D. Maintain Iterations as a safe zone
Three members of Team C created a new workflow to speed up the testing process. They spent an entire Iteration designing the process but discovered, just before implementation, that the system could not support the workflow. The rest of the team was excited to hear what was learned from the failed experiment.
Which of the following characteristics of a high-performing Agile Team is Team C demonstrating?
A. Enjoy their work and working together
B. Trust each other, allowing for both healthy conflict and reliance on others
C. Fostering an environment for taking risks without fear of embarrassment or punishment
D. Accountable to each other and the organization for reliably completing quality work
When is the System Demo conducted during program execution?
A. Each week
B. When the System Team is ready
C. At the end of every Iteration
D. Only when all the stakeholders are available
Which type of decision should remain centralized even in a decentralized decision-making environment?
A. Decisions that come with a high cost of delay
B. Decisions that deliver large and broad economic benefit
C. Decisions that require local information
D. Decisions that are made frequently
Which of the following Agile Team responsibilities is associated with the Iteration Retrospective?
A. Improve relentlessly
B. Apply systems thinking
C. Take an economic view
D. Connect to the customer
Which responsibility belongs to the Product Owner in the team?
A. To foster normalized estimating within the team
B. To facilitate team meetings and drive Agile behavior
C. To foster adoption of Agile technical practices
D. To sequence backlog items to program priorities, events, and dependencies
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Scaled Agile exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your SP-SAFE-PRACTITIONER exam preparations and Scaled Agile certification application, do not hesitate to visit our Vcedump.com to find your solutions here.