Which of the following products are routinely produced as part of the Managing a Stage Boundary process?
1.
Next Stage Plan
2.
Updated Project Plan
3.
Exception Plan
4.
Updated Business Case
A. 1,2,3
B. 2,3,4
C. 1,3,4
D. 1,2,4
Once the project has been authorized, within which process are checks made for any necessary changes to the project management team or their role descriptions?
A. Managing a Stage Boundary
B. Starting Up a Project
C. Closing a Project
D. Directing a Project
Which process is predicated on dividing the project into management stages?
A. Starting Up a Project
B. Managing a Stage Boundary
C. Closing a Project
D. Initiating a Project
What takes place within the Managing a Stage Boundary process?
A. Periodic review of progress against the Stage Plan
B. Approval and acceptance of all products created during the current stage
C. Escalation of Issue Reports and risks captured during the current stage
D. Review and if necessary update the Project Initiation Documentation
Which process has a specific objective to record any information or lessons that can help later stages of this project and/or other projects?
A. Directing a Project
B. Managing Product Delivery
C. Managing a Stage Boundary
D. Initiating a Project
Which of the following is a specific objective of the Managing Product Delivery process?
A. The project management team is focused on delivery within the tolerances laid down
B. The Business Case is kept under review
C. Attention is focused on delivery of the stage's products D. Team Managers, team members and suppliers are clear as to what is to be produced and what is the expected effort, cost or timescale
Which process would check and accept Work Packages?
A. Controlling a Stage
B. Managing Product Delivery
C. Directing a project
D. Managing a Stage Boundary
What is an objective of the Managing a Stage Boundary process?
A. Request authorization to start the next stage
B. Ensure that all threats and opportunities for the current stage have been closed
C. Make certain that work on products allocated to the team for the next stage is authorized and agreed
D. Implement actions to resolve tolerance deviations from the Stage Plan
If used, in which process would a Team Plan be created?
A. Managing Product Delivery
B. Managing a Stage Boundary
C. Directing a Project
D. Controlling a Stage
The Managing Product Delivery process views the project from which role's perspective?
A. Team Manager
B. Senior Supplier
C. Project Support
D. Project Manager
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PRINCE2 exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PRINCE2-FOUNDATION exam preparations and PRINCE2 certification application, do not hesitate to visit our Vcedump.com to find your solutions here.