Which of the following is NOT a type of performance measure?
A. Planned Value.
B. Earned Value.
C. Estimate to complete.
D. Cost variance.
For which of the following reasons can the cost baseline be updated?
A. Due to cost savings.
B. Due to delays in project execution.
C. Due to customer driven scope change.
D. Due to subcontractor's price change.
What is NOT a key element for the lower level WBS structure set up in SAP from a cost and progress manager perspective?
A. FandC requirement.
B. Ability to execute customer orders.
C. To support IPM setup.
D. Cost reporting capability for identified project scope.
What is the relationship between sales items (SI's) and service orders in the care contract?
A. An SvO can have multiple SI's, but an SI line in the care contract can have only one SvO.
B. There is no relationship or connection between SIs and SvOs in the care contract.
C. An SvO can have only one SI, and an SI line in the care contract can have only one SvO.
D. An SvO can have only one SI, but an SI line in the care contract can have multiple SvOs.
Which milestone(s) must always be completed before invoicing?
A. Provisional acceptance.
B. Final acceptance.
C. Internal acceptance.
D. It depends on the contractual terms.
A risk response which involves eliminating a threat is called:
A. mitigation.
B. deflection.
C. avoidance.
D. transfer.
Which is not a factor in choosing a subcontractor?
A. Complexity of requirements.
B. Price competition.
C. Competency.
D. Personal relationship with management.
Which of the following is NOT part of the IPM suite?
A. Sales management.
B. Site data management.
C. Change management.
D. Document management.
Which of the following is NOT an example of cost of poor quality?
A. Rework.
B. Quality training.
C. Scrap.
D. Warranty costs.
Which data can be imported directly from 4C into PPR?
A. GS cost baseline, materialized risk, GS cost EAC.
B. GS and MBB actual costs, materialized risk, non conformance costs, sellable additional works.
C. GS as sold cost estimate, risk contingency consumed, sellable additional works.
D. GS cost EAC, budgeted risk, sub-contractor claims.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Nokia exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PDM_2002001060 exam preparations and Nokia certification application, do not hesitate to visit our Vcedump.com to find your solutions here.