What is the primary purpose of sales packages?
A. Sales packages are a method primarily for planning quantity contract set-up in SAP P20.
B. Sales packages are a method to define the services scope in customer sales, subcontracting and related management of the same across different tools.
C. Sales packages are an element in a customer contract and as such are the key input for the planning of project cash flow in the relevant tools.
D. Sales packages are an element in a customer contract and as such are the key input for the planning of project acceptance in the relevant tools.
What is NCC in Nokia?
A. Any cost overruns.
B. All subcontractor extra work costs.
C. Materialized risks.
D. All extra site visit costs.
The product line is unable to meet a software release committed timeline. Due to this delay, resources dedicated to the installation need to remain available for an additional month. Additionally, the project will be liable to pay penalties based on contract conditions. How should these extra costs be reported?
A. Extra resources cost which will be booked via SvO with an accounting indicator relevant for resources caused NCC (Pre- or Post-P8), and penalties will be booked via SVO with an accounting indicator relevant for execution.
B. Extra resources cost which will be booked via SvO with an accounting indicator relevant for product caused NCC (Pre- or Post-P8), and penalties will be part of the claim log.
C. Both costs will be booked via SvO with an accounting indicator relevant for product caused NCC (Preor Post-P8).
D. Both costs will be booked via SvO with an accounting indicator relevant for resources caused NCC.
What is the primary KPI generated from the Site Quality module of IPM?
A. Rollout accuracy (RA).
B. Project Site Quality Index (P-SQI).
C. Site Invoice Lead Time (SILT).
D. Telecom Implementation Lead Time (TILT).
Prior to contract signing, the project manager is required to set up the PBM plan and quality gate process. If there is no ERP, how should the project manager charge their time?
A. To an approved pre-sales WTR code based on the SWF/CRM ID, as no PO is yet received.
B. To an approved project planning and initiation cost SvO.
C. To an SvO for an existing related project as it is not worthwhile to create an SvO for this small activity.
D. The PM should not be working on these activities prior to the contract being signed.
The technique of analyzing the sequence of activities with the least amount of scheduling flexibility is called the:
A. critical path method.
B. flowchart.
C. Precedence diagram method.
D. Work breakdown Structure.
What transactions still can be done after the project financial closure?
A. Services can be accepted.
B. Charges against the project.
C. Invoice processing.
D. No transactions.
Which of the following activities will contribute to reducing the project asset levels and improving project cash flow performance of an NI project?
A. Combining different customer acceptances in order to bundle customer invoices.
B. Making sure all task completed milestones are updated in IPM without delay.
C. Ensuring that the local project warehouse never runs out of inventory.
D. Ensuring that the equipment is delivered to the site at least 2 days before the site will be ready for installation.
What are the most important pieces of information from the customer contract for a CPM?
A. Deliverables, schedule, related costs, WBS structure, acceptance and payment procedures and reporting requirements.
B. Deliverables, schedule, ordering process, WBS structure, acceptance and payment procedures and reporting requirements.
C. Schedule, ordering process and structure, costs and resources, acceptance and payment procedures and reporting requirements.
D. Schedule, ordering process and structure, deliverables and sales packages, acceptance and payment procedures and reporting requirements.
To meet the requirements of the project through effective contract management, it is best to:
A. prepare a unique contract.
B. use standard clauses in contracts.
C. avoid using contractual documents.
D. mix standard and unique clauses.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only Nokia exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PDM_2002001060 exam preparations and Nokia certification application, do not hesitate to visit our Vcedump.com to find your solutions here.