Marketing has requested a significant change in the mix for a product family. The requested change falls between the demand and the planning time fences. The most appropriate action by the master scheduler is to:
A. reject the request.
B. accept the request.
C. forward the request to senior management.
D. check the availability of required material.
If the total part failure rate of a machine is 0.00055 failures per hour, what would be the mean time between failures (MTBF) in hours?
A. 1,818.2
B. 59.99945
C. 1.98
D. 0.99945
Components of an organization's Immediate industry and competitive environment Include:
A. political factors.
B. interest rates.
C. substitute products.
D. sociocultural forces.
In which of the following phases of the product life cycle is product price most effective in influencing demand?
A. Introduction
B. Growth
C. Maturity
D. Decline
Price negotiation is most appropriate when purchasing which of the following product categories?
A. Commodities
B. Standard products
C. Items of small value
D. Made-to-order (MTO) items
Given the bill of material (BOM) information below and independent requirements of 10 pieces (pcs) per week of Component A and 20 pieces (pcs) per week of Component B, what is the weekly gross requirement of component F?
A. 80
B. 120
C. 160
D. 200
Which of the following planning modules considers the shortest-range planning goals?
A. Capacity requirementsplanning(CRP)
B. Input/output analysis
C. Resource planning
D. Rough-cut capacity planning (RCCP)
Capacity requirements planning (CRP) is applicable primarily In companies operating In an environment where:
A. backlog is very low.
B. the status of work orders is disregarded.
C. lean principles are used.
D. material requirements planning (MRP) is used.
The question below is based on the following information:
Work Center 1 has an available capacity of 1,200 hours per month. Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 3?
A. 50
B. 150
C. 1.250
D. 3.750
What priority control technique is most appropriate for a firm using a cellular production system?
A. Shortest processing time (SPT) rule
B. Distribution requirements planning (DRP)
C. Pull production activity control (PAC)
D. Push production activity control (PAC)
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only APICS exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CPIM exam preparations and APICS certification application, do not hesitate to visit our Vcedump.com to find your solutions here.