Exam Details

  • Exam Code
    :PMI-SP
  • Exam Name
    :PMI Scheduling Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :323 Q&As
  • Last Updated
    :Nov 06, 2024

PMI PMI Certification PMI-SP Questions & Answers

  • Question 281:

    Winnie is the project manager for her company. She has been recording the actual durations of the project work to determine the actual progress of her project. Winnie needs to generate an updated project schedule based on project performance. She is using the supporting schedule data, manual scheduling methods, and her project management software to perform schedule network analysis. What other tool Winnie can use to help and generate an updated project schedule?

    A. Critical path method

    B. Schedule management plan

    C. Scheduling tool

    D. Critical chain method

  • Question 282:

    Examine the figure given below: Which path is considered the critical path?

    A. ACDFJ

    B. ACGIJ

    C. ABEFJ

    D. ABDFJ

  • Question 283:

    Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?

    A. Develop schedule process

    B. Risk register

    C. Project risk management plan

    D. Activity attributes

  • Question 284:

    You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so you will need to update the schedule and the schedule baseline. The schedule baseline is a component of what?

    A. Project calendar

    B. Project constraints

    C. Project objectives

    D. Project management plan

  • Question 285:

    John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the importance of communication in the project. He would like to show the number of stakeholder communication channels in the project. Based on this information how many communication channels exist within this project?

    A. 3000

    B. 79

    C. 80

    D. 3160

  • Question 286:

    You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for moving materials. You also have to ensure that delivery trucks do not have to wait in a queue and that workers on the upper floors are able to get their deliveries on time. Which type of scheduling would be required in such a scenario?

    A. Critical path scheduling

    B. Time-oriented scheduling

    C. Resource-oriented scheduling

    D. Network scheduling

  • Question 287:

    Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few hours to the duration estimate in case something goes wrong during the completion of the work activity. Sarah, the project sponsor, does not approve of this and warns Jim of Parkinson's Law. What is Parkinson's Law?

    A. People will behave based on what their behavior brings them.

    B. As employees do repetitive tasks, duration should decrease.

    C. Work expands to fill the amount of time allotted to it.

    D. An exponential increase labor does not correlate to an exponential decrease in duration.

  • Question 288:

    Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your project. If your project has a BAC of $650,000 and you've spent $385,000 to date, what is the schedule variance value?

    A. -$75,500

    B. -$390,000

    C. -$487,500

    D. -$65,000

  • Question 289:

    You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

    A. Preventive action

    B. Defect repair validation

    C. Implemented corrective action

    D. Quality control

  • Question 290:

    Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

    A. 0.98

    B. -$16,677

    C. 1.07

    D. 0.94

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-SP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.