Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.
What should the risk manager do?
A. Schedule a meeting to review and develop realistic risk thresholds with the project team.
B. Motivate and influence the project team with risk engagement activities like workshops.
C. Ensure that risk management responsibilities are clearly identified in the risk management plan.
D. Ensure that the risk language used by all stakeholders is consistent with the risk management plan.
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
A. Accept the identified risk because other stakeholders feel that there are higher priority risks to address.
B. Mitigate the identified risk in order to reduce the probability of impacting the stakeholder's team.
C. Escalate the identified risk to the project sponsor and allow them to determine the best course of action.
D. Add the identified risk to the risk register for future probability and impact analysis.
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?
A. Risk analysis
B. Risk identification
C. Risk treatment
D. Risk evaluation
A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.
Which technique should the risk manager use in this situation?
A. Brainstorming
B. Delphi method
C. Focus group
D. Checklist analysis
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment
What should the risk manager do?
A. Confirm the risk triggers are still valid.
B. Ask the architect to develop acceptance criteria.
C. Review the feature with the project team.
D. Escalate the issue to the project board.
A project lihat was in the execution phase for the last six months was put on hold and was eventually cancelled after numerous scope related challenges. It was decided to re-plan the scope and divide the project into multiple projects to have better insight into end objectives. As part of the project start up. the project manager is developing the risk planning for the project.
What three artifacts should the project manager consult or review during this process? (Choose three.)
A. Project contracts
B. Lessons learned registers from analogous projects
C. Risk register
D. Risk management plan
E. Code of regulations
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
A. Add contingencies to other tasks to mitigate similar risks.
B. Reassess risks with a new assumptions and constraints analysis.
C. Review the risk response plan looking for lessons learned.
D. Log the event in the issue log and update the project management plan.
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?
A. Ensure sufficient resources are available
B. Revise the risk management plan
C. Update the risk register
D. Meet with the project's stakeholders
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next?
A. Recommend the removal of risks to the project manager to reduce project risk exposure.
B. Advise the client that the project has exhausted contingency.
C. Quantify the risk exposure that exceeds project contingency.
D. Generate reports to assess and communicate the project risk level.
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
A. Implement the risk response strategies into the risk plan.
B. Inform the sponsor that these risks should be added according to experience.
C. Add the risks to the risk register and determine a contingency.
D. Discuss and evaluate the identified risks with the project team.
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-RMP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.