  • Question 501:

    Which is a report of all the work that is "done"?

    A. Burndown

    B. Completion chart

    C. Kanban chart

    D. Sashimi

  • Question 502:

    Product Backlog Items (PBI) described as emergent, are expected to:

    A. Become new technology requirements

    B. Grow and change over time as users' stories are completed

    C. Become the highest priority items

    D. Be the most recent stories added to the backlog

  • Question 503:

    In Agile,________________is the primary measure of progress:

    A. Accelerated Burndown chart

    B. Reduced risk

    C. Increased customer satisfaction

    D. Working software

  • Question 504:

    User Stories are:

    A. Negotiable

    B. Baselined and not allowed to change

    C. Created by the Agile Project Manager

    D. The foundation of the roadmap

  • Question 505:

    This role would be responsible for determining when a release can occur:

    A. Product Owner

    B. Scrum Master

    C. Development Team

    D. Agile Project Manager

  • Question 506:

    Agile uses a number sequence for estimating. The series of numbers begin with 0, 1, 1 and are calculated by adding the previous two numbers to get the next number. This number sequence is called:

    A. Sashimi

    B. Velocity

    C. Capacity

    D. Fibonacci

  • Question 507:

    Acronym describing the attributes of a product backlog:

    A. DEEP

    B. INVEST

    C. ITERA

    D. DESPO

  • Question 508:

    When maintaining the product backlog, this role represents the interests of the stakeholders, and ensures the value of the work completed:

    A. Scrum Master

    B. Agile Project Manager

    C. Product Owner

    D. Sponsor

  • Question 509:

    Which should NOT take place at the daily Scrum?

    A. The Product Owner gives an update

    B. The Scrum Mater manages the time-box

    C. The Development Team answers the three questions

    D. Issues are raised and documented

  • Question 510:

    On an Agile team, the project leader works to remove impediments from blocking the team's progress. This is known as what type of leadership?

    A. Servant

    B. Command and control

    C. Consensus-driven

    D. Functional management

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-ACP exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.