Exam Details

  • Exam Code
    :PMI-001
  • Exam Name
    :Project Management Professional
  • Certification
    :PMI Certification
  • Vendor
    :PMI
  • Total Questions
    :920 Q&As
  • Last Updated
    :Apr 30, 2024

PMI PMI Certification PMI-001 Questions & Answers

  • Question 871:

    A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

    A. Benchmarking.

    B. Context diagrams.

    C. Brainstorming.

    D. Prototyping.

  • Question 872:

    Which item is an example of personnel assessment?

    A. Resource calendar

    B. Tight matrix

    C. Team-building activity

    D. Focus group

  • Question 873:

    The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

    A. Plan Human Resource Management.

    B. Acquire Project Team.

    C. Manage Project Team.

    D. Develop Project Team.

  • Question 874:

    Market conditions and published commercial information are examples of which input to the Estimate Costs process?

    A. Scope baseline

    B. Organizational process assets

    C. Enterprise environmental factors

    D. Risk register

  • Question 875:

    An output of the Develop Project Team process is:

    A. Organizational process assets.

    B. Enterprise environmental factors updates.

    C. Project staff assignments.

    D. Organizational charts and position descriptions.

  • Question 876:

    The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:

    A. Work performance information.

    B. Inspections and audits.

    C. Payment systems.

    D. Procurement performance reviews.

  • Question 877:

    The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

    A. Project Communications Management

    B. Project Integration Management

    C. Project Risk Management

    D. Project Scope Management

  • Question 878:

    Change requests are processed for review and disposition according to which process?

    A. Control Quality

    B. Control Scope

    C. Monitor and Control Project Work

    D. Perform Integrated Change Control

  • Question 879:

    Which input to the Plan Risk Management process provides information on high-level risks?

    A. Project charter

    B. Enterprise environmental factors

    C. Stakeholder register

    D. Organizational process assets

  • Question 880:

    Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?

    A. Work performance data

    B. Project documents

    C. Scope baseline

    D. Requirements documentation

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.