  • Question 431:

    Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

    A. updates.

    B. defect repairs.

    C. preventive actions.

    D. corrective actions.

  • Question 432:

    Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?

    A. Project

    B. Functional

    C. Program

    D. Portfolio

  • Question 433:

    One of the tools and techniques of the Manage Project Team process is:

    A. organization charts.

    B. ground rules.

    C. organizational theory,

    D. conflict management.

  • Question 434:

    A method to manage stakeholder expectations in the scope statement is to clearly:

    A. state the guiding principles of the organization.

    B. identify alternatives to generate different approaches.

    C. state what is out of scope.

    D. outline the results of the Delphi technique.

  • Question 435:

    Labor, materials, equipment, and supplies are examples of:

    A. Resource attributes.

    B. Resource types.

    C. Resource categories.

    D. Resource breakdown structures (RBS).

  • Question 436:

    Analogous cost estimating relies on which of the following techniques?

    A. Expert judgment

    B. Project management software

    C. Vendor bid analysis

    D. Reserve analysis

  • Question 437:

    Which of the following is an example of the simplest fixed-price contract?

    A. Purchase requisition

    B. Purchase order

    C. Verbal agreement

    D. Request for quote

  • Question 438:

    Which technique helps to determine the risks that have the most potential impact on a project?

    A. Cost risk simulation analysis

    B. Expected monetary value analysis

    C. Modeling and simulation

    D. Sensitivity analysis

  • Question 439:

    Which process involves identifying and documenting the logical relationships between project activities?

    A. Develop Schedule

    B. Sequence Activities

    C. Create WBS

    D. Applying leads and lags

  • Question 440:

    Which activity involves ensuring that the composition of a projects configuration items is correct?

    A. Configuration Identification

    B. Configuration Status Accounting

    C. Configuration Verification and Audit

    D. Configuration Quality Assurance

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.