  • Question 341:

    Testing falls into which of the following categories of cost of quality?

    A. Internal failure costs

    B. Prevention costs

    C. Appraisal costs

    D. External failure costs

  • Question 342:

    Another name for an Ishikawa diagram is:

    A. cause and effect diagram.

    B. control chart.

    C. flowchart.

    D. histogram.

  • Question 343:

    Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?

    A. Performance organizations

    B. Schedule baselines

    C. Work performance measurements

    D. Change requests

  • Question 344:

    Which of the following is an output of Direct and Manage Project Execution?

    A. Project management plan

    B. Change request status updates

    C. Organizational process assets updates

    D. Work performance information

  • Question 345:

    Which of the following is an input to Develop Human Resource Plan?

    A. Team performance assessment

    B. Roles and responsibilities

    C. Staffing management plan

    D. Enterprise environmental factors

  • Question 346:

    Which tool or technique is used in Close Procurements?

    A. Contract plan

    B. Procurement plan

    C. Closure process

    D. Procurement audits

  • Question 347:

    A required input for Create WBS is a project:

    A. quality plan.

    B. schedule network.

    C. management document update.

    D. scope statement.

  • Question 348:

    Which of the following statements is true regarding project and product lifecycles?

    A. A single product lifecycle may consist of multiple project lifecycles.

    B. A product lifecycle is always shorter than the project lifecycle.

    C. A single product lifecycle can only have one project lifecycle.

    D. A single project lifecycle may consist of multiple product lifecycles.

  • Question 349:

    In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?

    A. Start-to-start (SS)

    B. Start-to-finish (SF)

    C. Rnish-to-finish (FF)

    D. Finish-to-start (FS)

  • Question 350:

    Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

    A. -8000

    B. -2000

    C. 2000

    D. 8000

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your PMI-001 exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.