  • Question 41:

    Which of the following is NOT an output of the Control Scope process?

    A. Project document updates

    B. Work performance measurements

    C. Accepted deliverables

    D. Change requests

  • Question 42:

    Which of the following is a process of monitoring the status of the project and product scope?

    A. Control scope

    B. Perform quality control

    C. Identify risk

    D. Plan quality

  • Question 43:

    Which of the following processes is used to obtain formal acceptance of the project scope by the stakeholders?

    A. Expert judgment

    B. Identify risk

    C. Quality control

    D. Verify scope

  • Question 44:

    Which of the following process groups starts after the planning phase of a project is over?

    A. Monitoring and Controlling

    B. Initiation

    C. Testing

    D. Execution

  • Question 45:

    Which of the following types of organizations reduces duplication of work because responsibilities are clearly defined on a company-wide basis?

    A. Matrix

    B. Jury

    C. Functional

    D. Projectized

  • Question 46:

    Which of the following techniques is used for weather forecasting?

    A. Probabilistic forecasting

    B. Scenario building

    C. Simulation

    D. Delphi method

  • Question 47:

    How many steps are there in the Plan stage of the PDCA cycle?

    A. 4

    B. 5

    C. 3

    D. 6

  • Question 48:

    Which of the following phases utilizes the most project time and resources?

    A. Monitoring and controlling

    B. Planning

    C. Initiation

    D. Executing

  • Question 49:

    Which of the following contracts is generally considered to be the most risky for the buyer?

    A. Cost plus percentage of costs

    B. Cost plus incentive fee

    C. Time and materials

    D. Fixed fee

  • Question 50:

    Which of the following is a measure of progress achieved compared to progress planned on a project?

    A. Cost variance

    B. Schedule performance index

    C. Schedule variance

    D. Cost performance index

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GIAC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your GCPM exam preparations and GIAC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.