Fill in the blank with the appropriate term.
_______emphasizes on bringing out the best in a team to make sure that self development, positive
communication, leadership skills, and the skill to work together as a team to resolve problems are built
within the team.
Fill in the blank with the appropriate term.
______ (also called contractor conferences, vendor conferences, and pre-bid conferences) are meetings with prospective sellers prior to preparation of a bid or proposal.
Fill in the blank with the appropriate term.
The______ defines the period in which, during the development of the project scope statement, a clear
and very thorough project scope statement narrative is documented.
Fill in the blank with the appropriate term.
The______ defines the period in which, during the development of the project scope statement, a clear
and very thorough project scope statement narrative is documented.
Fill in the blank with the appropriate word. ______refers to conveying a message from an individual person to another or to several people, whether verbally or non-verbally
Which one of the following best describes a quality metric?
A. An operational definition in specific terms what something is and how the quality control processes measures it.
B. A value associated with a project process that may be measured in the cost of achieving the process results.
C. An operational definition in specific terms what something is and how the quality assurance processes measures it.
D. The ability of an entity to satisfy stated and implied needs.
You work as a project manager for PassGuide Inc. You report the project details directly to the vice president and the administrator of your organization. In which of the following types of organization structures are you working?
A. Jury
B. Functional
C. Projectized
D. Matrix
You work as a project manager for PassGuide Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?
A. 0.87
B. 0.80
C. 0.86
D. 0.84
You are the project manager of a computer upgrade project. You and the vendor are in dispute over the deliverables the vendor was to provide and configure. What document can best describe how you and the vendor are to proceed if there is a claim against the vendor?
A. Procurement management plan
B. Enterprise environmental factors
C. Contract
D. Project cost management plan
Which of the following are inputs of the Control Scope process? Each correct answer represents a complete solution. Choose all that apply.
A. Change request
B. Requirements documentation
C. Project management plan
D. Work performance information
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GIAC exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your GCPM exam preparations and GIAC certification application, do not hesitate to visit our Vcedump.com to find your solutions here.