Exam Details

  • Exam Code
    :CAPM
  • Exam Name
    :Certified Associate in Project Management (PMI-100)
  • Certification
    :CAPM
  • Vendor
    :PMI
  • Total Questions
    :1283 Q&As
  • Last Updated
    :Apr 30, 2024

PMI CAPM CAPM Questions & Answers

  • Question 41:

    A project manager requesting industry groups and consultants to recommend project intervention is relying on:

    A. Communication models.

    B. Stakeholder participation.

    C. Expert judgment

    D. Enterprise environmental factors.

  • Question 42:

    Funding limit reconciliation is a tool and technique of which Project Cost Management process?

    A. Estimate Costs

    B. Control Costs

    C. Plan Cost Management

    D. Determine Budget

  • Question 43:

    Which Process Group includes the Manage Stakeholder Engagement process?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Initiating

  • Question 44:

    Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

    A. Business case

    B. Work breakdown structure

    C. Requirements documentation

    D. Risk register

  • Question 45:

    The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

    A. Close Procurements.

    B. Control Procurements.

    C. Plan Procurements.

    D. Conduct Procurements.

  • Question 46:

    Analytical techniques are a tool and technique of which process in Project Procurement Management?

    A. Plan Procurement Management

    B. Control Procurements

    C. Conduct Procurements

    D. Close Procurements

  • Question 47:

    Which quality tool incorporates the upper and lower specification limits allowed within an agreement?

    A. Control chart

    B. Flowchart

    C. Checksheet

    D. Pareto diagram

  • Question 48:

    An intentional activity to modify a nonconforming product or product component is called:

    A. defect repair

    B. work repair

    C. corrective action

    D. preventive action

  • Question 49:

    Grouping the stakeholders based on their level of authority and their level of concern regarding project outcomes describes which classification model for stakeholder analysis?

    A. Influence/impact grid

    B. Power/influence grid

    C. Power/interest grid

    D. Salience model

  • Question 50:

    Variance and trend analysis is a tool and technique used in which process?

    A. Perform Qualitative Risk Analysis

    B. Perform Quantitative Risk Analysis

    C. Control Risks

    D. Plan Risk Responses

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.