  • Question 61:

    In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

    A. Technical approach

    B. Technical capability

    C. Business size and type

    D. Production capacity and interest

  • Question 62:

    Which type of organizational structure is displayed in the diagram provided?

    A. Balanced matrix

    B. Projectized

    C. Strong matrix

    D. Functional

  • Question 63:

    Outputs of the Control Communications process include:

    A. expert judgment and change requests.

    B. work performance information and change requests.

    C. organizational process asset updates and an issue log.

    D. project management plan updates and an issue log.

  • Question 64:

    Which Manage Communications tool or technique focuses on identifying and managing barriers?

    A. Communication methods

    B. Information technology

    C. Communication models

    D. Information management systems

  • Question 65:

    The scope management plan and scope baseline are contained in:

    A. organizational process assets

    B. a requirements traceability matrix

    C. the project charter

    D. the project management plan

  • Question 66:

    The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:

    A. work package

    B. deliverable

    C. milestone

    D. activity

  • Question 67:

    When closing a project or phase, part of the process may require the use of which type of analysis?

    A. Reserve analysis

    B. Regression analysis

    C. Document analysis

    D. Product analysis

  • Question 68:

    Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

    A. Critical path method

    B. Critical chain method

    C. Resource leveling

    D. Schedule network analysis

  • Question 69:

    In a typical project, project managers spend most of their time:

    A. Estimating

    B. Scheduling

    C. Controlling

    D. Communicating

  • Question 70:

    For a stakeholder with low interest and high power, the project manager should:

    A. Monitor the stakeholder.

    B. Manage the stakeholder closely.

    C. Keep the stakeholder satisfied.

    D. Keep the stakeholder informed.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only PMI exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your CAPM exam preparations and PMI certification application, do not hesitate to visit our Vcedump.com to find your solutions here.