Some tools are geared more for developer use. For the 5 tools listed, which statement BEST details those for developers
i) Performance testing tools. ii) Coverage measurement tools. iii) Test comparators. iv) Dynamic analysis tools. v) Incident management tools.
A. i, iii. and iv. are more for developers.
B. ii. and iv. are more for developers.
C. ii, iii. and iv. are more for developers.
D. ii. and iii. are more for developers.
With which of the following categories is a test comparator tool USUALLY associated?
A. Tool support for performance and monitoring.
B. Tool support for static testing.
C. Tool support for test execution and logging.
D. Tool support for the management of testing and tests.
Which activities form part of test planning?
i) developing test cases.
ii) defining the overall approach to testing.
iii) assigning resources.
iv) building the test environment.
v) writing test conditions.
A. i, ii and iv are true, iii and v are false.
B. ii and iii are true, i, iv and v are false.
C. iv and v are true, i, ii and iii are false.
D. i, ii, and iii are true iv and v are false.
Which of the following defines the expected results of a test?
A. Test case specification.
B. Test design specification.
C. Test procedure specification.
D. Test results.
Who would USUALLY perform debugging activities?
A. Developers.
B. Analysts.
C. Testers.
D. Incident Managers.
Which of the following would you NOT usually find on a software incident report?
A. The name and/or organisational position of the person raising the problem.
B. Version of the Software Under Test.
C. Suggestions as to how to fix the problem.
D. Actual and expected results.
A wholesaler sells printer cartridges. The minimum order quantity is 5. There is a 20% discount for orders of 100 or more printer cartridges. You have been asked to prepare test cases using various values for the number of printer cartridges ordered. Which of the following groups contain three test inputs that would be generated using Boundary Value Analysis?
A. 5, 6, 20
B. 4, 5, 80.
C. 4, 5, 99.
D. 1, 20, 100.
Which of the following activities should be performed during the selection and implementation of a testing tool? i) Investigate the organisation test process.
i) Investigate the organisation's test process.
ii) Conduct a proof of concept.
iii) Implement the selected tool on a project behind schedule to save time.
iv) Identify coaching and mentoring requirements for the use of the selected tool.
A. i, ii, iii.
B. ii, iii, iv.
C. i, iii, iv.
D. i, ii, iv.
What is the MAIN benefit of designing tests early in the life cycle?
A. It is cheaper than designing tests during the test phases.
B. It helps prevent defects from being introduced into the code.
C. Tests designed early are more effective than tests designed later.
D. It saves time during the testing phases when testers are busy.
Which of the following benefits are MOST likely to be achieved by using test tools?
i) Easy to access information about tests and testing.
ii) Reduced maintenance of testware.
iii) Easy and cheap to implement.
iv) Greater consistency of tests.
A. ii and iv
B. ii and iii
C. i and iv
D. i and iii
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only ISEB exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your BH0-004 exam preparations and ISEB certification application, do not hesitate to visit our Vcedump.com to find your solutions here.