  • Question 681:

    What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

    A. 0.50

    B. 0.67

    C. 1.50

    D. 2.00

  • Question 682:

    Scope, schedule, and cost parameters are integrated in the:

    A. Performance measurement baseline.

    B. Analysis of project forecasts,

    C. Summary of changes approved in a period,

    D. Analysis of past performance.

  • Question 683:

    A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:

    A. Adaptive

    B. Predictive

    C. Incremental

    D. Iterative

  • Question 684:

    A large portion of a projects budget is typically expended on the processes in which Process Group?

    A. Executing

    B. Planning

    C. Monitoring and Controlling

    D. Closing

  • Question 685:

    A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

    A. Efficient

    B. Effective

    C. Push

    D. Pull

  • Question 686:

    An input to the Manage Project Team process is:

    A. Work performance reports.

    B. Change requests.

    C. Activity resource requirements.

    D. Enterprise environmental factors.

  • Question 687:

    Which input provides suppliers with a clear set of goals, requirements, and outcomes?

    A. Procurement statement of work

    B. Purchase order

    C. Source selection criteria

    D. Bidder conference

  • Question 688:

    Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

    A. Mandatory

    B. Discretionary

    C. Internal

    D. External

  • Question 689:

    During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

    A. Monitor and Control Project Work

    B. Perform Quality Assurance

    C. Close Project or Phase

    D. Control Scope

  • Question 690:

    A technique used to determine the cause and degree of difference between baseline and actual performance is:

    A. Product analysis.

    B. Variance analysis.

    C. Document analysis,

    D. Decomposition.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.