  • Question 621:

    In which Knowledge Area is the project charter developed?

    A. Project Cost Management

    B. Project Scope Management

    C. Project Time Management

    D. Project Integration Management

  • Question 622:

    Which tool or technique is used to manage change requests and the resulting decisions?

    A. Change control tools

    B. Expert judgment

    C. Delphi technique

    D. Change log

  • Question 623:

    The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

    A. Work packages.

    B. Accepted deliverables.

    C. The WBS dictionary.

    D. The scope baseline.

  • Question 624:

    Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

    A. Plan Procurement Management

    B. Control Procurements

    C. Collect Requirements

    D. Plan Cost Management

  • Question 625:

    Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

    A. Stakeholder register

    B. Scope management plan

    C. Stakeholder management plan

    D. Project charter

  • Question 626:

    Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

    A. Project Risk Management

    B. Project Human Resource Management

    C. Project Scope Management

    D. Project Stakeholder Management

  • Question 627:

    Inputs to the Plan Schedule Management process include:

    A. Organizational process assets and the project charter,

    B. Enterprise environmental factors and schedule tools.

    C. Time tables and Pareto diagrams.

    D. Activity attributes and resource calendars.

  • Question 628:

    A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

    A. Identify Risks

    B. Control Risks

    C. Perform Quantitative Risk Analysis

    D. Perform Qualitative Risk Analysis

  • Question 629:

    Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

    A. Direct and Manage Project Work

    B. Develop Project Management Plan

    C. Plan Quality Management

    D. Monitor and Control Project Work

  • Question 630:

    Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

    A. Direct

    B. Interactive

    C. Pull

    D. Push

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.