  • Question 591:

    Typical outcomes of a project include:

    A. Products, services, and improvements.

    B. Products, programs, and services.

    C. Improvements, portfolios, and services.

    D. Improvements, processes, and products.

  • Question 592:

    A project manager builds consensus and overcomes obstacles by employing which communication technique?

    A. Listening

    B. Facilitation

    C. Meeting management

    D. Presentation

  • Question 593:

    Which Control Quality tool is also known as an arrow diagram?

    A. Matrix diagram

    B. Affinity diagram

    C. Tree diagram

    D. Activity network diagram

  • Question 594:

    The Monitoring and Controlling Process Group includes processes that:

    A. Establish the scope, objectives, and course of action of a project,

    B. Define a new project or a new phase of an existing project.

    C. Track, review, and regulate the progress and performance of a project.

    D. Complete the work defined in the project management plan.

  • Question 595:

    Sensitivity analysis is typically displayed as a/an: A. Decision tree diagram.

    B. Tornado diagram.

    C. Pareto diagram.

    D. Ishikawa diagram.

  • Question 596:

    Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

    A. External

    B. Internal

    C. Mandatory

    D. Discretionary

  • Question 597:

    Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

    A. Cost management plan.

    B. Work performance information.

    C. Quality management plan.

    D. Work breakdown structure.

  • Question 598:

    The basis of identification for current or potential problems to support later claims or new procurements is provided by:

    A. A risk urgency assessment.

    B. The scope baseline.

    C. Work performance information.

    D. Procurement audits.

  • Question 599:

    Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

    A. Requirements documentation

    B. Requirements traceability matrix

    C. Project management plan updates

    D. Project documents updates

  • Question 600:

    Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

    A. Only once, at the beginning

    B. At the beginning and the end

    C. Once during each phase

    D. Repeatedly

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.