  • Question 481:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the schedule performance index (5PI) for Task 4?

    A. 0.83

    B. 0.9

    C. 1.11

    D. 1.33

  • Question 482:

    One of the key benefits of the Plan Human Resource Management process is that it:

    A. outlines team selection guidelines and team member responsibilities.

    B. establishes project roles and responsibilities.

    C. improves teamwork, interpersonal skills, and competencies.

    D. provides an accurate appraisal of team member performance.

  • Question 483:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the cost variance (CV) for Task 6?

    A. -2,000

    B. 0

    C. 1,000

    D. 2,000

  • Question 484:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the schedulevariance (SV) for Task 8?

    A. -2,000

    B. -1,000

    C. 1,000

    D. 2,000

  • Question 485:

    A tool and technique used in the Develop Project Charter process is:

    A. change control tools

    B. expert judgment

    C. meetings

    D. analytical techniques

  • Question 486:

    The following chart contains information about the tasks in a project.

    Based on the chart, what is the cost performance index (CPI) for Task 2?

    A. 0.8

    B. 1

    C. 1.25

    D. 1.8

  • Question 487:

    A risk that arises as a direct result of implementing a risk response is called a:

    A. contingent risk

    B. residual risk

    C. potential risk

    D. secondary risk

  • Question 488:

    The purpose of developing a project scope management plan is to:

    A. Manage the timely completion of the project.

    B. Ensure that the project includes all of the work required.

    C. Make sure the project will satisfy the needs for which it was begun.

    D. Reduce the risk of negative events in the project.

  • Question 489:

    Which is an enterprise environmental factor?

    A. Marketplace conditions

    B. Policies and procedures C. Project files from previous projects

    D. Lessons learned from previous projects

  • Question 490:

    Project Stakeholder Management focuses on:

    A. project staff assignments

    B. project tea m acquisition

    C. managing conflicting interests

    D. communication methods

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.