Exam Details

  • Exam Code
    :APM-001
  • Exam Name
    :Certified Associate in Project Management (APM)
  • Certification
    :GAQM Certifications
  • Vendor
    :GAQM
  • Total Questions
    :704 Q&As
  • Last Updated
    :Jul 01, 2025

GAQM GAQM Certifications APM-001 Questions & Answers

  • Question 451:

    In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

    A. Technical approach

    B. Technical capability

    C. Business size and type

    D. Production capacity and interest

  • Question 452:

    Stakeholder communication requirements should be included as a component of:

    A. enterprise environmental factors

    B. organizational process assets

    C. the project management plan

    D. the stakeholder register

  • Question 453:

    Which element does a project charter contain?

    A. Management reserves

    B. Work breakdown structure

    C. Stakeholder list

    D. Stakeholder register

  • Question 454:

    In a typical project, project managers spend most of their time:

    A. Estimating

    B. Scheduling

    C. Controlling

    D. Communicating

  • Question 455:

    When closing a project or phase, part of the process may require the use of which type of analysis?

    A. Reserve analysis

    B. Regression analysis

    C. Document analysis

    D. Product analysis

  • Question 456:

    Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

    A. Critical path method

    B. Critical chain method

    C. Resource leveling

    D. Schedule network analysis

  • Question 457:

    For a stakeholder with low interest and high power, the project manager should:

    A. Monitor the stakeholder.

    B. Manage the stakeholder closely.

    C. Keep the stakeholder satisfied.

    D. Keep the stakeholder informed.

  • Question 458:

    A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:

    A. triangular distribution

    B. tornado diagram

    C. beta distribution

    D. fishbone diagram

  • Question 459:

    A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

    A. Strong

    B. Weak

    C. Managed

    D. Balanced

  • Question 460:

    Project Scope Management is primarily concerned with:

    A. Developing a detailed description of the project and product.

    B. Determining how requirements will be analyzed, documented, and managed.

    C. Defining and controlling what is and is not included in the project.

    D. Formalizing acceptance of the completed project deliverables.

Tips on How to Prepare for the Exams

Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.