Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
A. Histograms
B. Scatter diagrams
C. Flowcharts
D. Checksheets
Which of the following is a narrative description of products, services, or results to be delivered by a project?
A. Project statement of work
B. Business case
C. Accepted deliverable
D. Work performance information
A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:
A. Historical information and the lessons-learned database.
B. Historical information and the stakeholder register.
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information.
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
A. Organizational process assets
B. A work breakdown structure
C. The project management plan
D. Enterprise environmental factors
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
A. Supportive
B. Leading
C. Neutral
D. Resistant
The formal and informal interaction with others in an organization industry, or professional environment is known as:
A. negotiation
B. organizational theory
C. meeting
D. networking
Which process is included in the Project Integration Management Knowledge Area?
A. Manage Project Team
B. Collect Requirements
C. Sequence Activities
D. Direct and Manage Project Work
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
A. Define Activities.
B. Sequence Activities.
C. Define Scope.
D. Control Schedule.
Which document includes the project scope, major deliverables, assumptions, and constraints?
A. Project charter
B. Project scope statement
C. Scope management plan
D. Project document updates
When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?
A. Bottom-up
B. Parametric
C. Analogous
D. Three-point
Nowadays, the certification exams become more and more important and required by more and more enterprises when applying for a job. But how to prepare for the exam effectively? How to prepare for the exam in a short time with less efforts? How to get a ideal result and how to find the most reliable resources? Here on Vcedump.com, you will find all the answers. Vcedump.com provide not only GAQM exam questions, answers and explanations but also complete assistance on your exam preparation and certification application. If you are confused on your APM-001 exam preparations and GAQM certification application, do not hesitate to visit our Vcedump.com to find your solutions here.